The de-stacking activity has been completed(TCO-DSME)

by Admin posted Jun 29, 2020
?

Shortcut

PrevPrev Article

NextNext Article

ESCClose

Larger Font Smaller Font Up Down Go comment Print

 

We are proudly announcing that the de-stacking activity for the TCO-FGP/WPMP has been completed by ISSAC & KOKS.

 

The activity is seperating each module(total 81 modules) by 2 or 3 layers to be transfered through the Volga-Don canal safely. With close communication and collaboration with the Client, the activity has performed with the best quality and safety manner during last 29 months of working schedule.